Contents
2 Environmental Site Inspection and
Audit
4 Conclusion and Recommendation
Table
1.1: Contact Information of Key Personnel
Table
2.1: Summary of Environmental Site Inspections
Table
2.2: Construction Waste Statistics
Table
2.3: Monitoring Programme for Landscape and Visual
Table
2.4: Event and Action Plan for Landscape and Visual
Table
2.5: Landscape and Visual Construction Phase Audit Summary
Table
2.6: Status of Environmental Licences and Permits
Table
2.7: Status of Submissions under Environmental Permit
Figures
Figure 1.1 Location of Project
Appendices
Appendix A Project Organization for Environmental
Works
Appendix B Construction Programme
Appendix C Environmental
Mitigation Implementation Schedule (EMIS) for Construction Phase
Appendix E Cumulative Statistics on Complaints,
Notification of Summons and Successful Prosecutions
The
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HZMB
HKBCF) The Road Connection between HKBCF and the Airport, Chek
Lap Kok (the HKIA-HKBCF Road Connection Project)
serves to connect the HKBCF with the Hong Kong International Airport (HKIA).
The Environmental Impact Assessment (EIA) for the HKBCF project, which covered
the HKBCF Viaduct/Roads as a Designated Project (DP) based on the requirements
set out in Item A.8. (i.e., a road bridge more than 100 m in length between
abutments) in Part 1 of Schedule 2 to the Environmental Impact Assessment
Ordinance (EIAO) (Cap. 499), was completed and approved (EIA Register No.:
AEIAR-145/2009) and an Environmental Permit (EP) (EP No.: EP-353/2009) was
granted under the EIAO to the Highways Department (HyD).
A Further Environmental Permit (FEP) (EP No. FEP-01/353/2009/K) for the
construction of the Project was granted to Airport Authority Hong Kong (AAHK)
in December 2018 in accordance with Section 12 of EIAO. Afterwards, an
Environmental Monitoring and Audit Manual for HZMB HKBCF The Road Connection
between HKBCF and the Airport, Chek Lap Kok (the EM&A Manual) has been prepared to include appropriate
environmental monitoring and audit (EM&A) requirements in accordance with
the information and recommendations described in the EIA Report and by taking
into account the specific site conditions of the Project under the FEP.
Mott
MacDonald Hong Kong Limited (MMHK) was commissioned by the Airport Authority
Hong Kong (AAHK) to undertake the role of Environmental Team (ET) for carrying
out the EM&A works during the construction phase of the Project in
accordance with the EM&A Manual.
AECOM Asia Company Limited (AECOM) was employed by AAHK as the
Independent Environmental Checker (IEC) for the Project.
Site
clearance and preparation works started in August 2021, and the construction
works of the Project commenced on 4 October 2021. This is the 3rd Construction
Phase Monthly EM&A Report for the Project which summarises the monitoring
and audit findings of the EM&A programme during the reporting period from 1
to 31 December 2021.
Key
Construction Activities in the Reporting Period
The construction activities of the Project
carried out in the reporting period included excavation, bored pile and
pre-drilling works.
EM&A
Activities Conducted in the Reporting Period
The EM&A programme was undertaken in
accordance with the EM&A Manual of the Project. Environmental monitoring and audit works
including regular environmental site inspections of construction works,
monitoring and audit of landscape and visual mitigation measures were conducted
by the ET and the IEC in the reporting period.
Summary
of the monitoring and audit activities during the reporting period is listed
below:
●
Environmental
site inspection: 6, 17, 20 and 28 December 2021
●
Monitoring
and audit of landscape and visual mitigation measures: 6, 20 December 2021
Based
on information including ETs observations and Contractors site records, it is
noted that environmental pollution control and mitigation measures of the
Project were properly implemented during the reporting period.
Summary
Table
The
following table summarises the key findings of the EM&A programme during
the reporting period:
Remarks: ^ Refer to the Event and Action Plan provided
in the Landscape and Visual section.
Future
Key Issues
The
main works anticipated in the upcoming month are as follows:
● Excavation
● Bored pile
● Pre-drilling
● Temporary storage and treatment for excavated marine sediment
Under
the HKBCF project, the arrangements for the planning of the construction of the
HKBCF Viaduct/Roads were formulated based on the scenario with the existing
two-runway system (2RS) at the HKIA. The portion of the HKBCF Viaduct/Roads
falling within the boundary of the land corridor between HKBCF and HKIA were
originally planned to be constructed by Highways Department (HyD) of the Government of the Hong Kong Special
Administrative Region (HKSARG) as part of the HKBCF project.
With
the planned expansion of HKIA into a three-runway system (3RS), a revised
layout of the HKBCF Viaduct/Roads (the revised layout is hereinafter referred
to as the proposed HKIA-HKBCF Road Connection) was formulated as part of the
P282 Terminal 2 Expansion Design Consultancy of Airport Authority Hong Kong
(AAHK). The proposed HKIA-HKBCF Road Connection has taken the design of the 3RS
road network designed around the expanded T2 building into account. In addition
to preparing the detailed design, it was also considered that the proposed
HKIA-HKBCF Road Connection within the HKBCF boundary would be constructed by
AAHK instead of HyD along with the 3RS road network
planned within the Airport Island. Upon completion of the construction works,
the new HKIA-HKBCF Road Connection outside the Airport Island would be handed
over to HyD for future operation and maintenance.
The
EIA for the HKBCF project, which covered the HKBCF Viaduct/Roads as a
Designated Project (DP) based on the requirements set out in Item A.8. (i.e., a
road bridge more than 100 m in length between abutments) in Part 1 of Schedule
2 to the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), was
completed and approved (EIA Register No.: AEIAR-145/2009) and an Environmental
Permit (EP) (EP No.: EP-353/2009) was granted under the EIAO to HyD.
On the
other hand, the 3RS EIA had subsequently commenced and completed (EIA Register
No.: AEIAR-185/2014) by AAHK, and it has already taken the layout of the
proposed HKIA-HKBCF Road Connection into account and has assessed the relevant
cumulative environmental impacts. The planned change in implementation agent
from HyD to AAHK for the construction of the proposed
HKIA-HKBCF Road Connection outside the Airport Island would, involves a
transfer of corresponding responsibilities under the HKBCF EP from HyD to AAHK. To this end, an Environmental Review Report
(ERR) was prepared and submitted to Environmental Protection Department (EPD)
in November 2018 which concluded that the change of implementation agent from HyD to AAHK for the construction of HKIA-HKBCF Road
Connection would not result in any exceedance or violation of the environmental
performance requirements set out in the approved HKBCF and 3RS EIAs and the
mitigation measures identified in these EIAs remained relevant and valid. A
Further Environmental Permit (EP No. FEP-01/353/2009/K) for the construction of
the HKIA-HKBCF Road Connection (hereinafter referred to as the Project) was
granted to AAHK in December 2018 in accordance with Section 12 of EIAO.
Afterwards, an Environmental Monitoring and Audit Manual for HZMB HKBCF The
Road Connection between HKBCF and the Airport, Chek
Lap Kok (the EM&A Manual) has been prepared to
include appropriate environmental monitoring and audit (EM&A) requirements
in accordance with the information and recommendations described in the EIA
Report and by taking into account the specific site conditions of the Project
under the FEP.
The
Project consists of the construction of a road bridge more than 100 m in length
between abutments connecting between HKBCF and the HKIA which is part of the
work for HZMB-HKBCF. Location of the Project is shown in Figure
1.1.
Site
clearance and preparation works of the Project started in August 2021, and the
construction works commenced on 4 October 2021. The summary of construction
works programme can be referred to Section 1.4.
This
is the 3rd Construction Phase Monthly EM&A Report for the
Project which summarises the key findings of the EM&A programme during the
reporting period from 1 to 31 December 2021.
The
Projects organisation structure is presented in Appendix
A. Contact
details of the key personnel are presented in Table 1.1.
Table 1.1: Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Project Managers Representative (Airport Authority Hong Kong) |
Principal Manager, |
Lawrence
Tsui |
2183
2734 |
Environmental Team (ET) (Mott MacDonald Hong Kong Limited) |
Environmental Team Leader |
Heidi Yu |
2828 5704 |
Independent Environmental Checker (IEC) (AECOM Asia Company Limited) |
Independent Environmental Checker |
Roy Man |
3922 9141 |
Contractor (Gammon Engineering & Construction
Limited) |
Project Director |
Richard Ellis |
6201 5637 |
Environmental Officer |
Fanny Law |
6184 4650 |
The
construction programme is enclosed in Appendix
B.
The
main construction works carried out during the reporting period were as
follows:
●
Excavation
●
Bored
pile
●
Pre-drilling
The
construction phase EM&A programme involves waste monitoring, construction
stage bi-weekly landscape and visual monitoring, weekly site environmental
inspections and related auditing conducted by the ET, as well as site audit by
the IEC for at least once a month for checking the implementation of the
required environmental mitigation measures recommended in the approved
HZMB-HKBCF EIA Report.
The
EM&A programme has been following the recommendations presented in the
approved HZMB-HKBCF EIA Report and the EM&A Manual. A summary of
implementation status of the environmental mitigation measures for the
construction phase of the Project during the reporting period is provided in Appendix
C.
Implementations of environmental
mitigation measures recommended in the approved HZMB-HKBCF EIA Report for air
quality, noise, water quality, waste management, landscape and visual aspects
for the construction phase of the Project were monitored and audited by ET and
IEC through site environmental inspections of the construction works and
checking of Contractors records and submission of information.
Site inspection findings are summarised in
Section 2.2. Details of audit for waste management are provided in Section
2.3, while that for landscape and visual measures are provided in Section
2.4. A summary of implementation status of environmental protection and
pollution control as well as mitigation measures during the reporting period is
provided in Appendix
C.
Site inspections of the construction works
were carried out on a weekly basis by the ET and at least once per month by the
IEC to monitor the implementation of proper environmental pollution control and
mitigation measures for construction dust, construction noise, construction
waste and wastewater for the Project.
During the reporting period, site
inspections were carried out on 6, 17, 20 and 28 December 2021. Inspection
findings made during the site inspections and corrective actions undertaken by
the Contractor are summarised in Table
2.1.
Table 2.1:
Summary of Environmental Site Inspections
Findings and Recommendations |
Actions taken by the Contractor |
Status of Findings |
|
6 December 2021 |
1. Non-road Mobile Machinery (NRMM) label
on the generator was observed torn and faded. The Contractor was reminded to
replace the NRMM label. |
1. The NRMM label was replaced and
displayed on the generator. |
Closed on 9 December 2021. |
17 December 2021 |
No findings were identified. |
N/A |
N/A |
20 December 2021 |
No findings were identified. |
N/A |
N/A |
28 December 2021 |
1. Construction
materials were observed next to the surface drain with inadequate mitigation
measures. The Contractor should provide preventive measures (e.g. sand bags
barrier) to prevent the construction materials from entering the public
drainage system. 2. Signage
for temporary marine sediment storage
was missing. The Contractor should
provide clear signage for the container of temporary marine sediment storage
to avoid any potential contamination of marine sediment and other excavated
materials. 3. Inadequate
mitigation measures were observed in the marine sediment storage area, including
gaps between concrete blocks on three sides and bottom, covering of marine
sediment, collection of surface runoff, site demarcation, and marine sediment
handling logbook. The Contractor should provide gap filling with cement
grout, impermeable sheet, drainage and pump, temporary fencing with warning
notices for demarcation, and logbook and plan on-site showing the
contaminated zones. |
1. Sand
bag barrier was provided to the drain. 2. Label
for the temporary marine sediment storage container was displayed. 3. Gaps
were filled with cement grout to prevent leakage of leachate; impermeable
sheet was provided to properly cover marine sediment; temporary fencing with
warning notices were provided for demarcation; logbook and plan were provided
on-site. Trench and sandbag barriers were provided to retain potential
surface runoff. |
Closed
on 31 December 2021, 3 and 10 January 2022. |
N/A: Not Applicable
In
accordance with the EM&A Manual, the waste generated from construction
activities was audited once per week to determine if wastes are being managed
in accordance with the Waste Management Plan (WMP) prepared for the Project,
and any statutory and contractual requirements. All aspects of waste management
including waste generation, storage, transportation and disposal were assessed
during the audits.
The
Contractor has been registered as a chemical waste producer for the Project.
Construction and demolition (C&D) material sorting was carried out on site.
A sufficient number of receptacles were available for general refuse
collection.
Weekly
monitoring was carried out by the ET to check and monitor the implementation of
proper waste management practices during the construction phase according to
the requirement of the Waste Management Plan, EM&A Manual and the implementation schedule of the waste management
mitigation measures in Appendix
C.
Based
on updated information provided by the Contractor, construction waste generated
during the reporting period is summarised in Table
2.2.
Table 2.2: Construction Waste Statistics
|
C&D(1) Material
Stockpiled for Reuse or Recycle |
C&D Material Reused in the Project (m3) |
C&D Material Reused in other
Projects (m3) |
C&D Material Transferred to Public
Fill (m3) |
Chemical Waste (kg) |
Chemical Waste (l) |
General Refuse (tonne) |
|
December 2021(2) |
32.6 |
0 |
0 |
1029.2 |
0 |
0 |
11.38 |
|
Notes: (1)
C&D refers to
Construction and Demolition. (2)
The data was based
on the information provided by Contractor up to the submission date of this
Monthly EM&A Report, and might be updated in the forthcoming Monthly
EM&A Report. |
The
monthly summary of waste flow table is presented in Appendix D. There was no non-compliance of the WMP, statutory
and contractual requirements during the reporting period.
Marine
sediment was managed according to the EIA Report, Updated EM&A Manual and
Waste Management Plan of the Project. The sampling process was reported by the
Contractor and storage conditions of the excavated marine sediment as well as
associated records were inspected and checked by ET and verified by IEC to
ensure they were in compliance with the requirements as stipulated in the Waste
Management Plan. Sampling works and testing for marine sediment excavated was
on-going during the reporting period, while treatment process and final
backfilling location would be confirmed upon the testing results. The details
of the marine sediment sampling and testing, treatment and backfilling will be reported
in the subsequent EM&A Reports upon completion.
The
monitoring programme for detailed design, construction, establishment works and
long-term management (10 years) stages is presented in Table
2.3. Event and Action Plan for Landscape and
Visual impacts is stated in Table 2.4.
Table 2.3: Monitoring Programme for Landscape and
Visual
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Detailed Design** |
Checking of design works
against the recommendations of the landscape and visual impact assessments
within the EIA should be undertaken during detailed design phase, to ensure
that they fulfil the intention of the mitigation measures. Any changes to the design, including design
changes on site should also be checked. |
Not Required |
Not Required |
At the end of the Detailed
Design Phase |
Construction |
Checking
of the Contractors operations during the construction period. |
Report
on Contractor's compliance, by ET |
Counter signature of report by IEC |
Bi-weekly |
Establishment Works |
Checking of the planting works during the
12-month Establishment Period after completion of the construction works. |
Report on Contractor's compliance, by ET |
Counter signature of report by IEC |
Every two months |
Long Term Management (10 year) |
Monitoring
of the long-term management of the planting works in the period up to 10
years after completion of the construction works. |
Report
on Contractors compliance
by Maintenance Agency as appropriate |
Counter signature of report by Management Agency |
Annually |
Notes:
* |
The maintenance agency to be responsible for the
monitoring during long term management will be confirmed by HyD with the handed over of the new HKIA-HKBCF Road
Connection upon the completion of the construction work. |
** |
The detailed design of HKIA-HKBCF Road Connection
was completed. |
Table 2.4: Event and Action Plan for Landscape
and Visual
Event
Action Level |
Action |
|||
ET |
IEC |
PM |
Contractor |
|
Non-conformity
occurs |
§ Check
Contractors proposed remedial design conforms to the requirements of EP and
prepare checking report(s) |
§ Check
and endorse ETs report(s) § Check
and certify Contractors proposed remedial design |
§
Supervise the Contractor to carry out the proposed remediation work |
§ Propose
remedial design and carry out the proposed remediation work |
Checking
of Contractors compliance on applicable landscape and visual mitigation
measures were carried out by the ET bi-weekly during site inspections with
findings reported in site inspection records agreed by the IEC. Implementation
status of the landscape and visual mitigation measures is summarized below in
Table
2.5 and provided in Appendix
C.
Table 2.5: Landscape and Visual Construction
Phase Audit Summary
Landscape and Visual Mitigation
Measures during Construction |
Implementation
Status |
G1
Grass-hydroseed bare soil surface and stockpile areas |
The
implementation of mitigation measures was checked by ET during site
inspections. Implementation
of the measures G11 and V1 by Contractor was observed. Measures G1,
G2 and V2 were not applicable during the reporting period. |
G2
Add planting strip and automatic irrigation system if appropriate at some
portions of bridge or footbridge to screen bridge and traffic |
|
G11
All existing trees shall be carefully protected during construction |
|
V1
Minimize time for construction activities during construction period |
|
V2
Provide screen hoarding at the portion of the project site / works areas /
storage areas near Visual Sensitive Receivers (VSRs) who have close low-level
views to the Project during construction. |
The
valid environmental permits, licenses, and/or notifications on environmental
protection for this Project are summarised in Table
2.6. During the reporting period,
environmental related licenses and permits required for the construction
activities were checked by ET and IEC, and no non-compliance with environmental
statutory requirements was recorded.
Table 2.6: Status of Environmental Licences and
Permits
Statutory
Reference |
Description |
Permit
/Reference No. |
Status |
Environmental Impact Assessment Ordinance
(EIAO) |
Environmental Permit |
FEP-01/353/2009/K |
Approved and granted on 27 December 2018 |
Air Pollution Control Ordinance (APCO) |
Notification of Construction Work under APCO |
459017 (Form NA)* |
Receipt acknowledged by EPD on 27 August 2020* |
459469 (Form NB)* |
Receipt acknowledged by EPD on 4 September
2020* |
||
Noise Control Ordinance (NCO) |
Construction Noise Permit (General Works) |
GW-RS0886-21 |
Valid from 19 November 2021 to 16 May 2022 (Superseded by GW-RS0979-21) |
GW-RS0979-21 |
Valid from 19 December 2021 to 31 May 2022 |
||
Waste
Disposal Ordinance (WDO) |
Registration
as Chemical Waste Producer |
WPN-5218-951-G2898-01* |
Completion
of Registration on 28 September 2020* |
Bill
account for disposal |
7038224* |
Approval
granted from EPD on 8 September 2020* |
|
Water Pollution Control Ordinance (WPCO) |
Discharge License |
EPIC Reference No: 2108121 |
Application on 22 October 2021 (in progress) |
*Notes: Licences
and permits were applied by the Contractor for their contract areas which
include construction site areas for the Project and 3RS Project.
The current status of submissions under
the FEP is presented in Table
2.7.
Table 2.7:
Status of Submissions under Environmental Permit
FEP Condition |
Submission |
Status |
3.1 |
EM&A Manual |
Accepted by EPD on 11 November 2021 |
2.3 |
Management Organisation |
Accepted by EPD on 16 August 2021 |
2.4 |
Landscape and Visual Plan |
Accepted by EPD on 11 November 2021 |
2.5 |
Waste Management Plan |
Accepted by EPD on 26 September 2021 |
No construction activities-related
complaint was received during the reporting period.
Neither notification of summons nor
prosecution was received during the reporting period.
Statistics on environmental complaints,
notifications of summons and successful prosecutions are summarised in Appendix
E.
As informed by the Contractor, major
construction activities for the next month include excavation, bored pile,
pre-drilling and temporary storage and treatment for excavated marine sediment.
Potential environmental impacts arising
from the above construction activities are expected to be mainly associated
with dust, construction noise, waste management, excavated
marine sediment and wastewater issues. The implementation of required
mitigation measures by the Contractor will be monitored by the ET.
The weekly site inspections for December
2021 are tentatively scheduled on 3, 10, 17, 24 and 31 January 2022.
Major construction activities of the
Project carried out during the reporting period included excavation, bored pile
and pre-drilling works.
Environmental site inspections of the
construction works were carried out on a weekly basis by the ET and at least
once per month by the IEC to monitor the implementation of proper environmental
pollution control and mitigation measures. Site inspections were carried out on
6, 17, 20 and 28 December 2021. Remedial actions recommended for the
deficiencies identified during the site inspections were properly implemented
by the Contractor.
There were no environmental complaints received
during the reporting period.
No notification of summons or successful
prosecution was received during the reporting period.
The ET will keep track on the construction
works to confirm compliance of environmental requirements and the proper
implementation of all necessary mitigation measures.