Contents
2 Environmental Site Inspection and Audit
3 Conclusion and Recommendation
Tables
Table 1.1: Contact Information of Key Personnel
Table 2.1: Construction Waste Statistics
Table 2.2: Landscape and Visual – Construction Phase Audit Summary
Table 2.3: Status of Environmental
Licences and Permits
Table 2.4: Status of Submissions under Environmental Permit
Table 2.5: Status for Complaints, Notifications of Summons and Prosecutions
Figures
Figure 1.1 Location of Project
Appendices
Appendix A Project Organization for Environmental Works
Appendix
B Construction Programme
Appendix C Environmental Mitigation Implementation
Schedule (EMIS) for Construction Phase
The
“Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HZMB
HKBCF) – The Road Connection between HKBCF and the Airport, Chek Lap Kok” (the
HKIA-HKBCF Road Connection Project) serves to connect the HKBCF with the Hong
Kong International Airport (HKIA). The Environmental Impact Assessment (EIA)
for the HKBCF project, which covered the HKBCF Viaduct/Roads as a Designated
Project (DP) based on the requirements set out in Item A.8. (i.e., a road
bridge more than 100 m in length between abutments) in Part 1 of Schedule 2 to
the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), was completed
and approved (EIA Register No.: AEIAR-145/2009) and an Environmental Permit
(EP) (EP No.: EP-353/2009) was granted under the EIAO to the Highways
Department (HyD). A Further Environmental Permit (FEP) (EP No. FEP-01/353/2009/K)
for the construction of the Project was granted to Airport Authority Hong Kong
(AAHK) in December 2018 in accordance with Section 12 of EIAO. Afterwards, an
Environmental Monitoring and Audit Manual for HZMB HKBCF – The Road Connection
between HKBCF and the Airport, Chek Lap Kok (the EM&A Manual) has been
prepared to include appropriate environmental monitoring and audit (EM&A)
requirements in accordance with the information and recommendations described
in the EIA Report and by taking into account the specific site conditions of
the Project under the FEP.
Mott
MacDonald Hong Kong Limited (MMHK) was commissioned by the Airport Authority
Hong Kong (AAHK) to undertake the role of Environmental Team (ET) for carrying
out the EM&A works during the construction phase of the Project in
accordance with the EM&A Manual.
AECOM Asia Company Limited (AECOM) was employed by AAHK as the
Independent Environmental Checker (IEC) for the Project. Site clearance and
preparation works started in August 2021, and the construction works of the
Project commenced on 4 October 2021.
This
is the 7th Construction Phase Quarterly EM&A Report for the
Project which summarises the monitoring and audit findings of the EM&A
programme during the reporting period from 1 April to 30 June 2023.
Key Construction Activities in the Reporting Period
The construction activities of the Project carried out in the
reporting period included bored piling, excavation and
lateral supports (ELS) for pile cap, and pile cap construction.
EM&A Activities Conducted in the Reporting Period
The EM&A programme was undertaken in accordance with the
EM&A Manual of the Project. Environmental monitoring and audit works
including regular environmental site inspections of construction works,
monitoring and audit of landscape and visual mitigation measures were conducted
by the ET and the IEC in the reporting period.
Summary of the monitoring and audit activities during the reporting period is listed below:
Monitoring
and Audit Activities |
Number
of Sessions |
Environmental site inspection |
13 |
Monitoring and audit of landscape and visual
mitigation measures |
6 |
Based on information including ET’s observations and Contractor’s site records, it is noted that environmental pollution control and mitigation measures of the Project were properly addressed and implemented during the reporting period
Summary Table
The following table summarises the key findings of the EM&A programme during the reporting period:
Yes |
No |
Details |
Analysis / Recommendation / Remedial Actions |
|
Non-conformity^ |
|
ü |
No non-conformity was recorded. |
Nil |
Complaint Received |
|
ü |
No complaint was
received. |
Nil |
Notification of any summons and status of prosecutions |
|
ü |
No notification of summons or prosecution was received. |
Nil |
Change that affect the EM&A |
|
ü |
There was no reporting changes. |
Nil |
Remarks: ^ Refer to the Event and Action Plan provided in the Landscape and Visual section.
To
connect the Hong Kong-Zhuhai-Macao Bridge (HZMB) Hong Kong Boundary Crossing
Facilities (HKBCF) with the Hong Kong International Airport (HKIA), roads
including an elevated bridge structure (hereinafter referred to as “the HKBCF
Viaduct/Roads”) were proposed as part of the HKBCF project, as described in
Section 4.5 of the approved Environmental Impact Assessment (EIA) report of the
HKBCF project. The HKBCF Viaduct/Roads are located partly within the boundary
of the Airport Island near Terminal 2 (T2) and partly within the boundary of
the land corridor between HKBCF and the Airport Island, i.e., partly within the
HKBCF boundary.
Under
the HKBCF project, the arrangements for the planning of the construction of the
HKBCF Viaduct/Roads were formulated based on the scenario with the existing
two-runway system (2RS) at the HKIA. The portion of the HKBCF Viaduct/Roads
falling within the boundary of the land corridor between HKBCF and HKIA were
originally planned to be constructed by Highways Department (HyD) of the Government
of the Hong Kong Special Administrative Region (HKSARG) as part of the HKBCF
project.
With
the planned expansion of HKIA into a three-runway system (3RS), a revised
layout of the HKBCF Viaduct/Roads (the revised layout is hereinafter referred
to as the proposed “HKIA-HKBCF Road Connection”) was formulated as part of the
P282 Terminal 2 Expansion Design Consultancy of Airport Authority Hong Kong
(AAHK). The proposed HKIA-HKBCF Road Connection has taken the design of the 3RS
road network designed around the expanded T2 building into account. In addition
to preparing the detailed design, it was also considered that the proposed
HKIA-HKBCF Road Connection within the HKBCF boundary would be constructed by
AAHK instead of HyD along with the 3RS road network planned within the Airport
Island. Upon completion of the construction works, the new HKIA-HKBCF Road
Connection outside the Airport Island would be handed over to HyD for future
operation and maintenance.
The
EIA for the HKBCF project, which covered the HKBCF Viaduct/Roads as a
Designated Project (DP) based on the requirements set out in Item A.8. (i.e., a
road bridge more than 100 m in length between abutments) in Part 1 of Schedule
2 to the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), was completed
and approved (EIA Register No.: AEIAR-145/2009) and an Environmental Permit
(EP) (EP No.: EP-353/2009) was granted under the EIAO to HyD.
On the
other hand, the 3RS EIA had subsequently commenced and completed (EIA Register
No.: AEIAR-185/2014) by AAHK, and it has already taken the layout of the
proposed HKIA-HKBCF Road Connection into account and has assessed the relevant
cumulative environmental impacts. The planned change in implementation agent
from HyD to AAHK for the construction of the proposed HKIA-HKBCF Road
Connection outside the Airport Island would, involves a transfer of
corresponding responsibilities under the HKBCF EP from HyD to AAHK. To this
end, an Environmental Review Report (ERR) was prepared and submitted to
Environmental Protection Department (EPD) in November 2018 which concluded that
the change of implementation agent from HyD to AAHK for the construction of
HKIA-HKBCF Road Connection would not result in any exceedance or violation of
the environmental performance requirements set out in the approved HKBCF and
3RS EIAs and the mitigation measures identified in these EIAs remained relevant
and valid. A Further Environmental Permit (EP No. FEP-01/353/2009/K) for the
construction of the HKIA-HKBCF Road Connection (hereinafter referred to as “the
Project”) was granted to AAHK in December 2018 in accordance with Section 12 of
EIAO. Afterwards, an Environmental Monitoring and Audit Manual for HZMB HKBCF –
The Road Connection between HKBCF and the Airport, Chek Lap Kok (the EM&A Manual)
has been prepared to include appropriate environmental monitoring and audit
(EM&A) requirements in accordance with the information and recommendations
described in the EIA Report and by taking into account the specific site
conditions of the Project under the FEP.
The Project consists of the construction of a road bridge more than 100 m in length between abutments connecting between HKBCF and the HKIA which is part of the work for HZMB-HKBCF. Location of the Project area is shown in Figure 1.1.
Site clearance and preparation works of the Project started in August 2021, and the construction works commenced on 4 October 2021. The summary of construction works programme can be referred to the corresponding Monthly EM&A Reports.
This is the 7th Construction Phase Quarterly EM&A Report for the Project which summarises the key findings of the EM&A programme during the reporting period from 1 April to 30 June 2023.
The Project’s organisation structure is presented in Appendix A. Contact details of the key personnel are presented in Table 1.1.
Table 1.1: Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Project Manager’s Representative (Airport Authority Hong Kong) |
Principal
Manager, |
Lawrence Tsui |
2183 2734 |
Environmental Team (ET) (Mott MacDonald Hong Kong Limited) |
Environmental Team Leader |
Heidi Yu |
2828 5704 |
Independent Environmental Checker (IEC) (AECOM Asia Company Limited) |
Independent Environmental Checker |
Jackel Law |
3922 9376 |
Contractor (Gammon Engineering & Construction Limited) |
Project Director |
Richard Ellis |
6201 5637 |
Environmental Officer |
Fanny Law |
6184 4650 |
The construction works undertaken during the quarter included bored piling, excavation and lateral supports (ELS) for pile cap, and pile cap construction. The construction programme is enclosed in Appendix B.
The
construction phase EM&A programme involves waste monitoring, construction
stage bi-weekly landscape and visual monitoring, weekly site environmental
inspections and related auditing conducted by the ET, as well as site audit by
the IEC for at least once a month for checking the implementation of the
required environmental mitigation measures recommended in the approved
HZMB-HKBCF EIA Report. The EM&A requirements remained unchanged during the
reporting period.
The EM&A programme has been following the recommendations presented in the approved HZMB-HKBCF EIA Report and the EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix C.
Implementations
of environmental mitigation measures recommended in the approved HZMB-HKBCF EIA
Report for air quality, noise, water quality, waste management, landscape and
visual aspects for the construction phase of the Project were monitored and
audited by ET and IEC through site environmental inspections of the
construction works and checking of Contractor’s records and submission of
information.
Site inspection findings are summarised in Section 2.2. Audit for waste management is summarised in Section 2.3, while that for landscape and visual measures are summarised in Section 2.4.
Site inspections of
the construction works were carried out on a weekly basis by the ET and at
least once per month by the IEC to monitor the implementation of proper
environmental pollution control and mitigation measures for construction dust,
construction noise, construction waste and wastewater for the Project.
During the reporting
quarter, a total of 13 sessions of environmental site inspections were carried
out and site inspection findings are detailed in the monthly EM&A Reports.
Major site inspection findings that were closed out with corrective actions
undertaken by the Contractor are highlighted as follows:
1.
The
maintenance record of the wastewater treatment facility was not duly
completed. The Contractor should
properly complete the maintenance record of the wastewater treatment facility
daily. The Contractor subsequently completed the maintenance record properly.
2.
Water
in the settling chamber of the wastewater treatment facility was observed
turbid but there was no discharge. The Contractor should provide further
treatment for the wastewater prior to discharge, so that the discharge quality
could meet the discharge license requirement. Subsequently, the Contractor
provided proper treatment for the wastewater.
A summary of
implementation status of environmental protection and pollution control as well
as mitigation measures during the reporting period is provided in Appendix C.
In
accordance with the EM&A Manual, the waste generated from construction
activities was audited once per week to determine if wastes are being managed
in accordance with the Waste Management Plan (WMP) prepared for the Project,
and any statutory and contractual requirements. All aspects of waste management
including waste generation, storage, transportation and disposal were assessed
during the audits.
The
Contractor has been registered as a chemical waste producer for the Project.
Construction and demolition (C&D) material sorting was carried out on site.
Sufficient number of receptacles were available for general refuse collection.
Weekly
monitoring was carried out by the ET to check and monitor the implementation of
proper waste management practices during the construction phase according to
the requirement of the Waste Management Plan, EM&A Manual and the
implementation schedule of the waste management mitigation measures in Appendix C.
Summary of construction waste generated during the reporting period is presented in Table 2.1 based on updated information provided by the Contractor.
Table 2.1: Construction Waste Statistics
|
C&D(1)
Material Stockpiled for Reuse or Recycle |
C&D
Material Reused in the Project |
C&D
Material Reused in other Projects |
C&D
Material Transferred to Public Fill |
Chemical
Waste |
Chemical
Waste |
General
Refuse |
|
|
(m3) |
(m3) |
(m3) |
(m3) |
(kg) |
(l) |
(tonne) |
|
April 2023 |
733.7 |
0 |
0 |
496.5 |
0 |
0 |
7.84 |
|
May 2023 |
0 |
0 |
0 |
140.7 |
0 |
0 |
12.92 |
|
June 2023 |
0 |
0 |
0 |
885.7 |
0 |
0 |
17.6 |
|
Note: (1) C&D refers to
Construction and Demolition. |
There
was no non-compliance of the WMP, statutory and contractual requirements during
the reporting period.
Based
on the contractor's additional information, which was reviewed and agreed by
relevant parties including AAHK, ET and IEC, the material excavated from bored
piles foundation works was not classified as marine sediment. The excavated
material would be handled as inert C&D material according to the WMP,
reused onsite or offsite for backfilling so that the need for offsite disposal
is minimised as far as practicable.
A
total of 6 sessions of bi-weekly monitoring and audit by checking of
Contractor’s compliance on applicable landscape and visual mitigation measures
were carried out by the ET during the reporting quarter, with findings reported
in site inspection records agreed by the IEC.
Implementation status of the landscape and visual mitigation measures is summarized below in Table 2.2 and provided in Appendix C.
Table 2.2: Landscape and Visual – Construction Phase Audit Summary
Landscape and Visual Mitigation Measures during Construction |
Implementation Status |
G1 – Grass-hydroseed bare soil surface and stockpile areas |
The
implementation of mitigation measures was checked by ET during site
inspections. Implementation
of the measures G11, V1, and V2 by the Contractor were observed. Measures G1 and G2 were not applicable during the reporting period. |
G2 – Add planting strip and automatic irrigation system if appropriate at some portions of bridge or footbridge to screen bridge and traffic |
|
G11 – All existing trees shall be carefully protected during construction |
|
V1 – Minimize time for construction activities during construction period |
|
V2 – Provide screen hoarding at the portion of the project site / works areas / storage areas near Visual Sensitive Receivers (VSRs) who have close low-level views to the Project during construction. |
During
the reporting period, environmental related licenses and permits required for
the construction activities were checked, and no non-compliance with
environmental statutory requirements was recorded.
Summary of the valid environmental permits, licenses, and/or notifications on environmental protection for this Project is presented in Table 2.3.
Table 2.3: Status of Environmental Licences
and Permits
Statutory Reference |
Description |
Permit /Reference No. |
Status |
Environmental
Impact Assessment Ordinance (EIAO) |
Environmental
Permit |
FEP-01/353/2009/K |
Approved and
granted on 27 December 2018 |
Air Pollution
Control Ordinance (APCO) |
Notification of
Construction Work under APCO |
459017 (Form NA)* |
Receipt
acknowledged by EPD on 27 August 2020* |
459469 (Form NB)* |
Receipt
acknowledged by EPD on 4 September 2020* (Superseded
by 493055) |
||
493055
(Form NB)* |
Receipt
acknowledged by EPD on 30 May 2023* |
||
Noise Control
Ordinance (NCO) |
Construction Noise
Permit (General Works) |
GW-RS0229-23* |
Valid
from 24 March 2023 to 21 September 2023* |
Waste
Disposal Ordinance (WDO) |
Registration
as Chemical Waste Producer |
WPN-5218-951-G2898-01* |
Completion
of Registration on 28 September 2020* |
Bill
account for disposal |
7038224* |
Approval
granted from EPD on 8 September 2020* |
|
Water Pollution
Control Ordinance (WPCO) |
Discharge License |
WT00037225-2020 |
Valid from 11
January 2022 to 30 April 2026 |
Note:
* Licences and permits were applied by the Contractor for their contract areas which include construction site areas for the Project and 3RS Project.
Summary of status of submissions under the FEP is presented in Table 2.4.
Table 2.4: Status of Submissions under Environmental Permit
FEP Condition |
Submission |
Status |
3.1 |
EM&A Manual |
Revised EM&A Manual was accepted by EPD |
2.3 |
Management Organisation |
Revised Management Organisation was accepted by EPD |
2.4 |
Landscape and Visual Plan |
Revised Landscape and Visual Plan was accepted by EPD |
2.5 |
Waste Management Plan |
Revised Waste Management Plan was accepted by EPD |
No
construction activities-related complaint was received during the reporting
period.
Neither notification of summons nor prosecution was received during the reporting period.
Cumulative statistics on
environmental complaints, notifications of summons and successful prosecutions
are summarised in Table 2.5.
Table 2.5: Status for Complaints,
Notifications of Summons and Prosecutions
Reporting
Period |
Cumulative Statistics |
||
|
Complaints |
Notifications
of Summons |
Prosecutions |
This reporting period |
0 |
0 |
0 |
From 4 October
2021 to end of the reporting period |
1 |
0 |
0 |
During
the 2nd quarter of 2023, major construction activities of the
Project carried out included bored piling, excavation
and lateral supports (ELS) for pile cap, and pile cap construction.
Environmental
site inspections of the construction works were carried out on a weekly basis
by the ET and at least once per month by the IEC to monitor the implementation
of proper environmental pollution control and mitigation measures. A total of
13 sessions of site inspections were carried out. Remedial actions for the
findings identified during the site inspections were properly implemented by
the Contractor.
There
were no environmental complaints, notification of summons or successful
prosecution received during the reporting period.